Domestic PPI, 22.1 Kauçuk ürünler
Series 22.1 of the Domestic Producer Price Index (2003=100). In price adjustment it can be bound to the other materials coefficient (b6) when the contracting authority finds it suits the work (art. 5/5).
Latest value
- September 2026 · 2003=100
- 4,421.78
- Monthly change
- +0.54%
- Annual change
- +22.42%
Period in the table: January 2003 – September 2026
- Latest value
- 4,421.78
- September 2026
- Period in the table
- January 2003 – September 2026
- Base year
- 2003=100 · CPA 2008 22.1
| Year | January | February | March | April | May | June | July | August | September | October | November | December |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026 | 3,755.06 | 3,862.08 | 3,880.32 | 4,016.55 | 4,167.59 | 4,313.23 | 4,344.87 | 4,398.19 | 4,421.78 | |||
| 2025 | 2,952.51 | 3,110.96 | 3,179.58 | 3,297.85 | 3,345.74 | 3,422.32 | 3,505.88 | 3,529.56 | 3,611.86 | 3,679.61 | 3,702.48 | 3,728.61 |
| 2024 | 2,370.76 | 2,467.00 | 2,550.19 | 2,624.32 | 2,644.71 | 2,707.96 | 2,752.31 | 2,831.15 | 2,847.14 | 2,904.83 | 2,909.38 | 2,928.77 |
| 2023 | 1,427.97 | 1,442.61 | 1,461.56 | 1,500.23 | 1,526.49 | 1,580.61 | 1,712.26 | 1,794.70 | 1,891.56 | 2,040.36 | 2,143.41 | 2,220.14 |
| 2022 | 885.26 | 907.84 | 961.48 | 1,020.76 | 1,109.06 | 1,158.06 | 1,220.99 | 1,256.10 | 1,281.85 | 1,299.03 | 1,323.82 | 1,388.26 |
| 2021 | 510.49 | 509.57 | 514.74 | 535.17 | 547.08 | 565.77 | 584.88 | 594.35 | 602.78 | 615.03 | 662.48 | 797.00 |
| 2020 | 395.92 | 400.97 | 404.16 | 413.75 | 418.89 | 426.19 | 431.78 | 439.61 | 458.03 | 471.68 | 490.87 | 493.76 |
| 2019 | 377.44 | 373.09 | 374.76 | 379.15 | 383.83 | 384.83 | 382.81 | 387.56 | 389.14 | 391.52 | 393.09 | 394.67 |
| 2018 | 259.95 | 261.82 | 265.48 | 271.71 | 276.02 | 286.38 | 293.94 | 314.35 | 367.03 | 376.81 | 379.83 | 376.04 |
| 2017 | 224.33 | 227.16 | 232.78 | 233.33 | 242.57 | 243.47 | 242.08 | 243.46 | 244.84 | 245.30 | 248.09 | 252.07 |
| 2016 | 213.05 | 212.59 | 211.50 | 211.40 | 211.94 | 215.46 | 216.75 | 213.07 | 210.40 | 215.37 | 217.77 | 221.74 |
| 2015 | 193.09 | 194.04 | 195.41 | 196.42 | 198.10 | 198.72 | 202.75 | 203.71 | 210.02 | 213.42 | 212.89 | 212.39 |
| 2014 | 186.74 | 193.42 | 193.66 | 197.06 | 196.62 | 196.68 | 199.39 | 197.26 | 198.45 | 198.71 | 198.81 | 197.79 |
| 2013 | 176.67 | 176.44 | 176.57 | 176.72 | 176.68 | 178.26 | 179.03 | 181.21 | 181.27 | 182.49 | 183.16 | 182.86 |
| 2012 | 169.95 | 170.37 | 170.83 | 172.93 | 173.27 | 173.16 | 172.76 | 172.82 | 173.15 | 173.42 | 173.63 | 173.92 |
| 2011 | 141.39 | 145.87 | 148.67 | 151.80 | 154.43 | 155.96 | 159.23 | 161.55 | 163.75 | 167.11 | 169.81 | 170.46 |
| 2010 | 133.79 | 134.28 | 136.12 | 135.95 | 135.26 | 137.18 | 138.24 | 139.29 | 137.88 | 140.28 | 140.54 | 141.56 |
| 2009 | 144.53 | 146.21 | 146.40 | 144.75 | 143.94 | 143.89 | 143.58 | 143.35 | 143.90 | 143.79 | 144.20 | 144.50 |
| 2008 | 123.02 | 125.42 | 126.91 | 131.41 | 132.77 | 132.61 | 135.92 | 134.98 | 135.55 | 136.01 | 139.08 | 140.45 |
| 2007 | 120.85 | 120.38 | 120.36 | 121.04 | 121.30 | 121.46 | 121.39 | 121.26 | 122.66 | 122.14 | 122.81 | 122.83 |
| 2006 | 104.64 | 105.17 | 105.32 | 107.36 | 108.57 | 114.49 | 117.63 | 120.63 | 120.42 | 119.92 | 120.15 | 122.18 |
| 2005 | 105.01 | 104.85 | 105.39 | 105.96 | 106.05 | 106.21 | 105.33 | 104.92 | 104.93 | 104.97 | 105.03 | 106.03 |
| 2004 | 96.46 | 96.79 | 96.32 | 96.54 | 99.80 | 100.35 | 101.89 | 101.93 | 102.93 | 103.24 | 104.95 | 106.10 |
| 2003 | 93.37 | 95.64 | 98.57 | 101.42 | 101.22 | 101.18 | 101.37 | 101.41 | 101.28 | 101.30 | 101.53 | 101.71 |
Free tool
Calculate a price adjustment with these indices
Enter your contract's coefficients; the indices fill in by themselves and the result follows the official formula.