Work out the rebar takeoff
Enter each bar size, count and length line by line to see the total length and the weight in kg and tonnes, with totals per bar size. No sign-up.
Reinforcement weight sheet
Enter one line per item or member. If the unit weight is left blank, the bar size's table value is used.
Enter the measures of the first line, or try the sample data.
How the reinforcement weight is found
Each line's total length is similar × count × length; its weight is that length times the bar size's weight per metre.
Weight (kg) = similar × count × length (m) × unit weight (kg/m)
Unit weight (kg/m) = π/4 × Ø² × 7.85 kg/dm³ (Ø in mm)
The table comes from this formula, rounded to 3 decimals: Ø8 0.395 · Ø10 0.617 · Ø12 0.888 · Ø14 1.208 · Ø16 1.578 · Ø20 2.466 · Ø25 3.853 · Ø32 6.313. The ز/162 shortcut is not used; it gives 0.889 for Ø12 and 1.210 for Ø14.
Rules
- Weight per metre table
- The weight per metre of 17 bar sizes from Ø6 to Ø50 comes from π/4 × Ø² × 7.85, to 3 decimals. Standards may give the nominal mass to other digits; you can enter your own value as the unit weight.
- Own unit weight
- Enter the unit weight by hand for another steel or standard. For an "Other" size it is required; lines with their own value are totalled apart.
- Waste and laps
- The tool adds no waste or lap allowance. Lap lengths are inside the bar length you enter; waste is up to the item description and the contract.
- Totals per bar size
- Each size's length and weight are totalled apart; the grand total is given in kg and tonnes. Tonnes are a thousandth of the kg, worked out from the exact value, not the rounded kg.
- No rounding along the way
- Lines and total are worked out with exact values; only the figure on screen is rounded: m, m², m³ and kg to 3 decimals, tonnes to 6. A copied value carries 8 decimals. A quantity rounded along the way leaves a gap that turns into money once multiplied by the unit price.
- Deduction lines
- Each thing to deduct goes on its own line, marked as a deduction; the sheet counts it negative. If the deductions exceed what was added, no total is given.
- Measurement rules come from the item description
- The "Measurement" clause of the item description and the technical specification decide which voids are deducted and how intersections are measured. The tool applies no void threshold and deducts no intersection by itself.
- Copying for Excel
- The sheet is copied with its header, lines and total as tab-separated text. Numbers use the page's decimal mark and no thousands separator; deductions carry a minus sign.
What this tool does not cover
It does not produce a bar bending schedule or cutting list, nor bending allowances.
It does not apply the item description's measurement clauses by itself, read quantities from drawings (DWG, IFC), or multiply quantities by unit prices into amounts.
About rebar takeoffs
- Price IndicesDomestic PPI sub-indices and CPI, monthly tables since 2012.
- Price Adjustment CalculatorPrice adjustment with the official formula, from Domestic PPI and CPI.
- Progress Payment Deductions CalculatorThe cover's VAT, every deduction from a) to k) and the net amount paid to the contractor, on one sheet.
- Index Change CalculatorHow Domestic PPI and CPI moved since your tender month, with the In/Io ratio.
- Work Experience Update CalculatorWhat a work experience certificate counts for in the tender you enter, with the right Domestic PPI months for its kind.
- Stamp Duty CalculatorThe 9.48 per mille stamp duty on a progress payment, with the yearly cap.
- VAT Withholding CalculatorThe VAT withheld on a progress payment, at the communiqué's rate for the work type.
- Withholding Tax CalculatorWithholding tax on a multi-year construction payment, at the rate for the work type and payment month.
- Performance Bond CalculatorThe performance bond on a bid, with the below-limit 9% rule and additional bonds.
- Minimum Labour CalculatorThe minimum labour to declare for the SGK clearance, the shortfall and its estimated premium.
- Advance Payment CalculatorThe advance, its 30% or one-third cap, the recovery rate and what comes off each progress payment.
- Work Increase CalculatorThe work increase room left under the 20% (unit price) or 10% (lump sum) limit.
- Completion Compensation Calculator5% of the shortfall when work ends below 80%, updated to the acceptance month by Domestic PPI.
- Delay Penalty CalculatorThe delay penalty from the first contract price, daily rate and days late, with the 15% cap.
- Work Duration CalculatorCompletion date from the site handover, days late, final acceptance and payment deadlines.
- Fuel PricesEPDK monthly averages by fuel type, for the fuel coefficient of a price adjustment.
Stop carrying rebar takeoffs into payments by hand
Takeoffs are entered by item, approved, and summed into the period's summary on their own.