Enter the work's total earnings, its minimum labour rate and the earnings declared to SGK to see the labour that must have been declared for the clearance certificate, the shortfall and its estimated premium. No sign-up.
Minimum labour and the premium on a shortfall
Take the amounts from the last progress payment and the dates from the acceptance report. Take the rate from the official list, by your work's nature.
Enter the work's total earnings and its minimum labour rate, or try the sample data.
How the minimum labour is found
After a tendered work is accepted, SGK checks whether the minimum labour it needed was declared. The calculation follows articles 110–112 of the Social Insurance Procedures Regulation (SSİY).
Minimum labour = Σ (total earnings × rate × 0.75)
Estimated premium = (minimum labour − declared) × premium rate
On a work that was not registered or declared no labour, the rate is not reduced by 25%. Each item is rounded to kuruş on its own. The premium on a shortfall falls in the month of the completion date and is assessed with the late-payment penalty and surcharge.
Rules
- The base
- The total earnings due to the employer: VAT excluded, material price adjustment and letter of credit included. The research follows the final acceptance, or a provisional acceptance without defects (SSİY art. 110/1).
- Less 25%
- The rate applies less 25%. If the workplace was not registered, or was registered but declared no labour at all, it is not reduced (SSİY art. 112/2).
- More than one line of work
- If the earnings were reported separately, each line takes its own rate; if not, the highest rate applies at the employer's written request. If the employer does not accept it, the Commission sets the rate (SSİY art. 110/4, Communiqué art. 5/2).
- Completion date
- The completion date in the approved provisional acceptance report; if the report lists defects, the date they were remedied. For work not subject to acceptance, the date the contracting authority reports (SSİY art. 110/6).
- Unfinished or terminated work
- The research runs on the progress payments paid. If none was paid, there is no research (SSİY art. 110/7).
- The premium on a shortfall
- The premium on the undeclared minimum labour falls in the month of the completion date and is served on the employer with the late-payment penalty and surcharge (SSİY art. 112/3). In 2026 the rate is 38.75%: invalidity, old-age and survivors 21%, general health 12.5%, short-term insurance 2.25%, unemployment insurance 3%.
- The rate list
- The rates are in the Communiqué's Annex 1; the list was renewed on 22.03.2023. The Commission sets the rate for work the list does not hold, and for work where the administration supplies material or pays the letter of credit (Communiqué art. 5/1). Communiqué art. 6/2 applies the lower of the old and new rates to work started before and finished after its publication; confirm with SGK how that applies to the 2023 list.
- What counts as declared
- Earnings and days declared before the work's start or after its acceptance do not count (SSİY art. 112/1). Subcontractors declare under the main employer's workplace file (SSİY art. 31/1).
What this tool does not cover
It does not calculate the person-days research on work whose contract fixes the headcount (SSİY art. 110/2), private construction (art. 111), converting foreign-currency payments at the CBRT selling rate of the payment day (art. 110/5), the late-payment penalty and surcharge, incentives or an SGK inspector's review. Works under Law 4734 art. 3/b get no minimum labour assessment (art. 112/10). It does not pick the rate from the list; you enter it.
Basis: Social Insurance Procedures Regulation art. 31 and 110–112 (as amended, Official Gazette 16.05.2026/33255); Communiqué on Minimum Labour Rates (Official Gazette 12.05.2010/27579) art. 5–6 and Annex 1 (Official Gazette 22.03.2023/32140); Law 5510 art. 81, 85 and 90; Law 4447 art. 49; Law 4735 art. 13. For information only.
About minimum labour
- Price IndicesDomestic PPI sub-indices and CPI, monthly tables since 2012.
- Price Adjustment CalculatorPrice adjustment with the official formula, from Domestic PPI and CPI.
- Progress Payment Deductions CalculatorThe cover's VAT, every deduction from a) to k) and the net amount paid to the contractor, on one sheet.
- Quantity Takeoff CalculatorRebar, concrete, formwork and excavation takeoffs: a measurement sheet with deductions, exact totals and a copy for Excel.
- Index Change CalculatorHow Domestic PPI and CPI moved since your tender month, with the In/Io ratio.
- Work Experience Update CalculatorWhat a work experience certificate counts for in the tender you enter, with the right Domestic PPI months for its kind.
- Stamp Duty CalculatorThe 9.48 per mille stamp duty on a progress payment, with the yearly cap.
- VAT Withholding CalculatorThe VAT withheld on a progress payment, at the communiqué's rate for the work type.
- Withholding Tax CalculatorWithholding tax on a multi-year construction payment, at the rate for the work type and payment month.
- Performance Bond CalculatorThe performance bond on a bid, with the below-limit 9% rule and additional bonds.
- Advance Payment CalculatorThe advance, its 30% or one-third cap, the recovery rate and what comes off each progress payment.
- Work Increase CalculatorThe work increase room left under the 20% (unit price) or 10% (lump sum) limit.
- Completion Compensation Calculator5% of the shortfall when work ends below 80%, updated to the acceptance month by Domestic PPI.
- Delay Penalty CalculatorThe delay penalty from the first contract price, daily rate and days late, with the 15% cap.
- Work Duration CalculatorCompletion date from the site handover, days late, final acceptance and payment deadlines.
- Fuel PricesEPDK monthly averages by fuel type, for the fuel coefficient of a price adjustment.
Record every step from acceptance to the bond release
Provisional and final acceptance, the clearance certificate and the bond release are tracked in one place in your project.