Skip to content
Free tool

Calculate the performance bond

Enter your bid to see the performance bond, 9% of the approximate cost if the bid is below the limit value, and the additional bond on work increases and price adjustment. No sign-up.

Calculator

Performance bond

Only the bid is required. The limit value and additional bond fields are optional.

Bid
₺

The winning bid, excluding VAT.

Limit value (optional)

If the bid is below the limit value, the bond is 9% of the approximate cost instead of 6% of the bid. A bid equal to the limit value keeps 6%.

₺

Left empty, 6% of the bid is taken.

₺

Needed when the bid is below the limit value.

Additional bond (optional)

While the contract runs, a 6% additional bond is taken on work increases and on price adjustment paid.

₺

Total of the approved work increases.

₺

Total price adjustment paid.

See the performance bond

Enter the bid, or try the sample data.

Method

How the performance bond is calculated

The performance bond is taken before the contract is signed; while it runs, additional bonds are added for work increases and price adjustment. The rates are fixed in law and regulation.

Formula

Performance bond = bid × 6%

If bid < limit value: approximate cost × 9%

Additional bond = (work increase + price adjustment) × 6%

Each part is rounded to the kuruş on its own and the total is taken after. The half returned at provisional acceptance is rounded to the kuruş too; the rest comes back after final acceptance.

Rules applied

6% of the bid
The performance bond is taken before the contract is signed, at 6% of the tender price (Public Procurement Law No. 4734, art. 43/1).
9% below the limit value
If the bid is below the limit value, the bond is 9% of the approximate cost; at or above it, 6% of the bid (Works Tenders Implementing Regulation art. 56/2). The law leaves it to the Public Procurement Authority to set this rate between 6% and 15% of the approximate cost (Law No. 4734, last paragraph of art. 43).
Additional bond
An additional bond of 6% is taken on the price adjustment paid and on any work increase (Public Procurement Contracts Law No. 4735, art. 12; Works Standard Contract art. 10.2.1).
Can come off payments
The additional bond on price adjustment can also be met by deducting it from progress payments (Law No. 4735, art. 12; Standard Contract art. 10.2.1).
Released in two steps
Half of the performance and additional bonds comes back after provisional acceptance and the rest after final acceptance, against a social security clearance (Law No. 4735, art. 13/a; General Specification for Works art. 45).
Bid bond of at least 3%
The bid bond given to take part cannot be less than 3% of the bid (Public Procurement Law No. 4734, art. 33; Implementing Regulation art. 56/1).

What this tool does not calculate

It does not work out the limit value itself; you enter the one your bid is compared with. The validity the administration sets for the performance bond letter (Implementing Regulation art. 56/6), the forms a bond may take and the different rule for consultancy tenders (4734 art. 43/2) are not taken into account. For the bank cost of the letter, you enter the term.

Legal basis: Public Procurement Law No. 4734, arts. 33 and 43; Public Procurement Contracts Law No. 4735, arts. 12 and 13; Works Tenders Implementing Regulation art. 56 (as amended, Official Gazette 7.6.2014/29023); Works Standard Contract art. 10.2.1; General Specification for Works art. 45. Bank cost of the letter: Expenditure Taxes Law arts. 28 and 33, Council of Ministers Decision 98/11591; VAT Law art. 17/4-e. For information only.

Frequently asked

About the performance bond

6% of the tender price (Law No. 4734, art. 43/1). On works, if the bid is below the limit value, 9% of the approximate cost is taken instead (Works Tenders Implementing Regulation art. 56/2).

On the approximate cost at 9%, not on the bid. On a job with an approximate cost of ₺10,000,000 and a bid below the limit value, the bond is ₺900,000. A bid equal to the limit value keeps 6% of the bid.

Where price adjustment is provided for, at 6% of the price adjustment paid, and at 6% of any work increase (Law No. 4735, art. 12; Works Standard Contract art. 10.2.1). The additional bond on price adjustment can also be met by deducting it from progress payments.

Once the provisional acceptance report is approved and the contractor owes the administration nothing, half of the performance and additional bonds comes back; the rest follows approval of the final acceptance report. A social security clearance is required (Law No. 4735, art. 13/a; General Specification for Works art. 45).

The bidder sets it, at no less than 3% of the bid (Law No. 4734, art. 33; Works Tenders Implementing Regulation art. 56/1).

On the "Bu Hakedişle Ödenen Fiyat Farkı Teminat Kesintisi" line among the deductions, as 6% of the price adjustment paid with that payment.

The performance bond letter is for the performance bond worked out on this page. The commission rate differs from bank to bank; enter your bank's rate and the term in the calculator's "Bank cost of the letter of guarantee" section to see the cost. BSMV of 5% is charged on the commission and the file fee; no VAT is charged.

Free tools

More tools for your progress payments

All free, none needs a sign-up.

All free tools
Leave the maths to us

Stop tracking bonds in a spreadsheet

Additional bonds come about by themselves with price adjustment and work increases, and a bond letter nearing expiry raises a warning.

Try it free