Skip to content
Free tool

Calculate price adjustment with the official formula

Enter the coefficients from your contract and let the indices load from TÜİK data. The calculation follows the formula in the Turkish Principles for Price Adjustment in Works Contracts. No sign-up.

Calculator

Your progress payment's price adjustment

Enter the coefficients exactly as the contracting authority's INDEX sheet lists them. Values of the series published on this site and EPDK fuel prices fill in by themselves.

Contract and payment

If the tender was announced before 26.03.2022, the contract falls under the 7-coefficient 2013 formula; this tool calculates the 8-coefficient 2022 formula. Sub-indices (23.51 etc.) are used for works announced on or after 01.09.2025; the tool draws this line by the tender date, so do not pick them for a work announced before that date.

The month the work was due under the work schedule. Current indices belong to this month.

₺

Value of the work done in the application month at contract prices.

₺

Optional. The advance deducted in this payment comes off An; not when Pn is below 1.

Coefficients

On each row, type the effective weight from the authority's document. A letter can carry several indices; leave unused letters at 0.

Σ Effective weightAll rows must add up to 1.000000
0.000000/ 1.000000incomplete
a

Labour

CPI General (2003=100, linked series from 2026), single index

Fixed coefficient 0.000000
Index
Io · no month chosen
—
In · no month chosen
—
b1

Other non-metallic mineral products

Domestic PPI 23 and its groups

Fixed coefficient 0.000000
Index
Io · no month chosen
—
In · no month chosen
—
b2

Iron and steel products

Domestic PPI 24 and its groups

Fixed coefficient 0.000000
Index
Io · no month chosen
—
In · no month chosen
—
b3

Motor fuel

EPDK sales price, from the bulletin

Fuel price table
Fixed coefficient 0.000000
Fuel type
AYo · price on no date chosen
—
AYn · no month chosen average
—

Taken from the EPDK bulletins: AYo is the sales price on the tender day, AYn the average sales price of the application month.

b4

Other solid or liquid fuels

Domestic PPI 19 and its groups

Fixed coefficient 0.000000
Index
Io · no month chosen
—
In · no month chosen
—
b5

Wood and cork products

Domestic PPI 16 and its groups

Fixed coefficient 0.000000
Index
Io · no month chosen
—
In · no month chosen
—
b6

Other materials

Domestic PPI series set by the authority; General if none

Fixed coefficient 0.000000
Index
Io · no month chosen
—
In · no month chosen
—
c

Depreciation of machinery and equipment

Domestic PPI 28 and its groups

Fixed coefficient 0.000000
Index
Io · no month chosen
—
In · no month chosen
—
Method

How price adjustment is calculated

In Turkish public works, price adjustment follows the formula in the Principles for Price Adjustment in Works Contracts. The calculator applies it as written.

Formula (art. 5/1)

F = An × B × (Pn − 1)

Pn = a(İn/İo) + b1(Çn/Ço) + b2(Dn/Do) + b3(AYn/AYo) + b4(Yn/Yo) + b5(Kn/Ko) + b6(Gn/Go) + c(Mn/Mo)

An is the value of the work done in the application month at contract prices. B is 0.90. Each term of Pn multiplies an input's weight by the ratio of its current to its base index.

Coefficients in the Pn formula and the indices they are bound to
CoefficientInputIndex
aLabourCPI General (2003=100, linked series from 2026), single index
b1Other non-metallic mineral productsDomestic PPI 23 and its groups
b2Iron and steel productsDomestic PPI 24 and its groups
b3Motor fuelEPDK sales price, from the bulletin
b4Other solid or liquid fuelsDomestic PPI 19 and its groups
b5Wood and cork productsDomestic PPI 16 and its groups
b6Other materialsDomestic PPI series set by the authority; General if none
cDepreciation of machinery and equipmentDomestic PPI 28 and its groups

Rules of the calculation

Base index (Io)
The index of the month the tender date falls in. For fuel, the sales price on the tender day. (art. 4/1-ı)
Current index (In)
The index of the application month; for fuel, that month's average sales price. The application month is when the work was due under the work schedule. (art. 4/1-ç, 4/1-i)
B = 0.90
The fixed coefficient of the formula; it does not vary by contract. (art. 5/2-c)
Coefficients add up to 1.00
The authority sets the coefficients in the tender documents so that they add up to one; they cannot change during the contract. (art. 5/3, 5/6)
Advance deduction
Where an advance was paid, the advance deducted in the payment comes off An before the calculation. Not when Pn is below one. (art. 6/6)
When Pn is below 1
The price adjustment is negative and is deducted from the payment. The Principles define it as an amount to be paid or deducted. (art. 4/1-e)
When an index is not yet published
The price adjustment is not calculated with the payment; it is calculated separately once the application month's indices are known. (art. 6/2)

What this tool does not calculate

It does not cover the lower-index rule for work behind schedule (art. 7/2), work carried on with penalties after the completion date, the provisional calculation with the previous month's indices when several payments fall in one month, the separate calculation of lump-sum and unit-price parts in mixed contracts, materials on site, or contracts under the 2013 Principles.

Indices are published by TÜİK and taken from the TCMB EVDS. Since January 2026 TÜİK has published the CPI on a 2025=100 base. The 2026 figures in the site's CPI General (2003=100) series are the 2025=100 series linked to the 2003=100 base (TCMB EVDS). The In/Io ratio comes out the same on both bases, apart from a very small rounding difference. The calculation is for information only.

Frequently asked

About price adjustment

With F = An × B × (Pn − 1). An is the value of the work done in the application month at contract prices, B is the fixed coefficient 0.90, and Pn is the sum of each input's weight times the ratio of its current to its base index. The coefficients and their indices are set out in the tender documents.

The index of the month the tender date falls in. For fuel, the sales price on the tender day is used. The current index (In) belongs to the application month; for fuel, that month's average sales price.

The price adjustment is negative and is deducted from the payment. The Principles define price adjustment as an amount to be paid or deducted; a negative result is not raised to zero.

Where an advance was paid, the price adjustment is calculated after the advance deducted in the payment comes off An. If Pn is below one, the advance is not deducted from An.

A payment drawn up before the indices are known carries no price adjustment; it is calculated separately once the application month's indices are published. For tenders announced on or after 01.09.2025, when several payments fall in one month, the previous month's indices are used and the difference is corrected in a later payment once the indices are known.

From the dealer sales prices EPDK publishes on its website. The base price is the tender-day price, the current price the application month's average. Prices are taken as the bulletin publishes them, VAT included, and used directly in the formula. This tool takes both prices from the EPDK bulletins by itself.

Free tools

More tools for your progress payments

All free, none needs a sign-up.

All free tools
Leave the maths to us

Stop doing this by hand on every payment

Enter the coefficients once; indices arrive every month and the price adjustment lands on the payment by itself.

Try it free