Skip to content
Free tool

Calculate the work increase limit

Enter the contract type and the first contract price to see how close the approved increases are to the limit, whether a new increase would pass it, and the additional bond it needs. No sign-up.

Calculator

Work increase

Enter amounts at contract prices, excluding VAT. Decreases do not free up room; add up the increases only.

Contract type
Contract type

On a unit-price contract, or the unit-price part of a mixed one, the share can be raised to 40%, contract by contract.

Contract
₺

The price before any increase, excluding VAT.

₺

Total of the increases so far.

₺

Optional; checked against the limit.

See the room left

Enter the contract type and the first contract price, or try the sample data.

Method

How the work increase limit is calculated

A work increase made necessary by something unforeseeable can be given to the same contractor up to a share that depends on the contract type. The share applies to the first contract price.

Formula

Limit = first contract price × share

Approved increases + new increase ≤ limit

The limit is rounded down to the kuruş, so adding the room shown never passes it. An increase exactly at the limit does not count as passing it.

Rules applied

20% on unit price, 10% on lump sum
Up to 20% of the contract price on unit-price contracts and 10% on turnkey lump-sum ones (General Specification art. 21/1, Law No. 4735 art. 24).
40% by presidential decision
On unit-price contracts and the unit-price part of a mixed one, the share can be raised to 40%, contract by contract (art. 21/2-3).
Two limits on a mixed contract
The lump-sum part is limited to 10% of its amount and the unit-price part to 20% (art. 21/3). Each limit applies on its own.
Conditions
The added work must stay within the contract's design, and splitting it from the main work must not be technically or economically possible (art. 21/1).
New-price work
For a tender announced before 01.09.2025, the amount is brought back to the tender date: divided by the application month's Pn, or with the Domestic PPI ratio where there is no price adjustment. For later tenders, the new unit price is set for the tender month where price adjustment applies and for the approval month where it does not; if the approval comes after the completion date, it is brought back to that date (art. 21/6).
Over the limit, the contract is wound up
If the work cannot be finished within these limits, no increase is made and the contract is wound up under the general provisions (art. 21/4).

What this tool does not calculate

It does not compute Pn; where price adjustment applies, you enter the application month's Pn. It does not judge whether the conditions for an increase are met. The completion compensation for work finished below 80% of the contract price has its own tool.

Calculate the completion compensation

Legal basis: Public Procurement Contracts Law No. 4735, art. 24; General Specification for Works art. 21; Works Tender Implementing Regulation, provisional art. 34; Works Standard Contract art. 10.2.1. For information only.

Frequently asked

About work increases

20% of the contract price on works tendered with unit prices and 10% on turnkey lump sum (Law No. 4735 art. 24, General Specification art. 21/1). On a mixed contract, the lump-sum part is limited to 10% and the unit-price part to 20%.

On unit-price contracts and the unit-price part of a mixed one, the President can raise the share to 40%, contract by contract (art. 21/2-3). Without such a decision the limit is 20%.

No. The limit applies to the gross total of increases; decreases do not reduce it. On work that ends below 80% of the contract price, the contractor is paid 5% of the gap between 80% of the price and the work done, at prices on the provisional-acceptance date (art. 21/5).

For a tender announced before 01.09.2025, the amount is divided by the application month's price adjustment factor (Pn) to bring it back to the tender date; where no price adjustment is provided, the Domestic PPI ratio between the application and tender months is used. For later tenders, work with price adjustment gets a new unit price set for the tender month and is not reduced; without price adjustment the approval month's price counts, brought back to the completion date if the approval comes after it (art. 21/6). The calculator's reduction section works out the amount and moves it into the new work increase field.

If the work cannot be finished within these limits, no increase is made and the contract is wound up under the general provisions. The work to be finished is then the quantity matching the first contract price (art. 21/4).

Yes, 6% of the increase (Works Standard Contract art. 10.2.1). Stamp duty of 9.48 per mille is also taken on the increase.

Free tools

More tools for your progress payments

All free, none needs a sign-up.

All free tools
Leave the maths to us

Stop tracking work increases in a spreadsheet

Every work increase is checked against the limit, and its additional bond comes about by itself.

Try it free